Hi Themba,
Glad it worked. Also, please note that resources are only imported under the following circumstances:
- if the demand for a resource exceeds its its availability (for example, if the annual resource yield is insufficient to meet demands)
If you do not want to show a certain resource as being "imported", you can use the Unmet Requirements variable under the Resources Branch to choose what happens when the demand for a resource exceeds its availability. By default, "MeetWithImports" is selected, but other options are available by clicking the orange "E" at the end of the Expression box.
Thanks,
Emily