• 69 views | 2 messages Discussion: LEAP
    Topic: Exercise 3 Para 3.2 Electricity GenerationSubscribe | Previous | Next
  • James Marett 6/9/2014

    1653 Views

    I have an evaluation version. In Ex 3 Para 3.2 which asks to change base year capacity, How do I change the base year value.

    Am I having problems because Transformation module is not included in Evaluation Version?
  • Taylor Binnington 6/10/2014
      Best Response

    1650 Views

    Hi James,

    No - the Evaluation Version does not restrict these actions.

    Be sure that you're making changes in the appropriate scenario. To modify the base year capacity for a power plant (or indeed, the base year value for any variable in LEAP), you would need to be in Current Accounts, selected from the Scenario drop down menu. Data that you enter while viewing a particular scenario will only affect your model from the First Scenario Year to the End Year. These years can be viewed/changed under Basic Parameters: Years.

    Best,

    Taylor