1278 Views Leap Training manual (2014) pg 23 "Next you will add three processes to represent the various power plants available"... followed by table values to add. (End of explanation)
1277 Views Hi,
1248 Views Taylor: Found the problem (outside of the stated set of assumptions). I was not creating a new model, I was editing a previous example which some data was already filled in. To show "Historical Values:" Under Transformation, under each process, right click on process, you must make sure that the Transformation Module properties, "Types of Data to Include" are checked.....which then displays multiple process variables, including Historical Values to be inputted.