Hi LEAP team,
Thanks for all the help so far! I had another question:
I'm trying to simulate a cap and trade scenario. I would like to optimize future investments that meet energy demand based off of capital costs. However, whenever I put capital costs into a new facility that has no initial capacity, LEAP won't return an optimized solution - all new renewable facilities remain at zero if their initial capacity is zero even if I have "Unlimited" as the value in the "Primary" "Resources" "Yield" parameter. I looked over example three and it doesn't seem to offer any resolution to my problem either.
I'm wondering if investment optimization is a LEAP functionality, or if I'm completely doing this wrong. I feel like it is, based off of the "Optimized" option in the "Electricity Generation" module, I think I'm just doing something completely wrong.