• 76 views | 1 messages Discussion: LEAP
    Topic: Smaller electricity generation than the electricity demandSubscribe | Previous | Next
  • Hana Kim 2/18/2020

    1 Like

    Dear community,

    I have built a model to simulate energy mix, but unexpectedly I have encountered a result that electricity generation cannot meet the electricity demand from a some point (in the model 2026).
    I assumed merit order dispatch for this model.
    The diagnostic messeges said: in some electricity generation processes, dispatch exceeded plants rated availability.

    Could you kindly let me know the possible causes and how to debug this challenge?

    Thank you in advance
    Hana