    Topic: No Electricity Generation CostsSubscribe | Previous | Next
  • Amanda Ngwenya 4/24/2021

    Hi team

    For my electricity generation system - my cost variables are not appearing (only interest as shown in attachement)). So I can't add capex, opex, etc. for my generation. I have double checked my settings, in cost tab - its calculating for 'Complete Energy System', in my Scope and scale tab - cost box is ticked however no tabs appearing in my model. Do you perhaps know what the issue could be here?

    Regards
    Amanda

    Generation Cost.png
  • Charlie Heaps 4/28/2021
      Best Response

    Make sure you have enabled the Costs checkboxes both in the Settings screen and in the relevant Module Properties screens. See screenshots.
    Screen2.png
    Screen.png