• 316 views | 3 messages Discussion: LEAP
    Topic: Hourly ProductionSubscribe | Previous | Next
  • Eleni Ntemou 12/4/2023

    Hello, I am working on a model that depicts the electricity production and consumption in Greece including seasonal storage. To achieve that, I have to insert the hourly production of RES plants, since I am basing the electricity production almost exclusively on solar PV, wind turbines and hydroelectric power plants. Please let me know if you have any suggestions on the topic.
    Bellow I have included the structure of the model

    Thank you.
  • Flady Cordero 12/8/2023
      Best Response

    Dear Eleni Ntemou,

    In your consultation, the structure to be modeled was not clear. If you want to model storage you should use optimization (NEMO)

    We suggest reviewing LEAP Training Materials:

    https://leap.sei.org/default.asp?action=trainingmaterials

    On YouTube (LEAP Platform):

    Sida LEAP Training Lecture #3: Energy Supply Modeling https://www.youtube.com/watch?v=6suTuLr9bOE

    Sida LEAP Training Lecture #6: Optimization Modeling with LEAP and NEMO https://www.youtube.com/watch?v=RjwtX2eL7tM&t=3945s

    Hoping they are useful, I say goodbye


    Flady Cordero


  • Esad Smajlovic 12/18/2023
      Best Response

    Hi,
    Have 8760 data on production in excell and based on that create load shape as availability form and then apply it as Maximum availability in the coresponding solar technology under transformation.