I am currently using LEAP (Version 2024.1.1.15, 64-Bit, Dictionary Version: 519) to model a least-cost long-term generation expansion plan. My objective is to optimize generation expansion planning; however, I am encountering issues specifically when using the NEMO optimization module. The Base scenarios works well as shown here
While the Business-As-Usual (BAU) scenario runs successfully, with power generation following the load demand patterns throughout the planning horizon, the optimized scenario presents the following challenges:
I have attached figures illustrating these issues for your reference. I would appreciate your guidance on resolving these problems to ensure that the optimized scenario accurately reflects a realistic generation expansion plan.